Reference: VLN-2026-PCC-001-TL | Start: 2026-05-12 | End: 2026-06-20
Engagement Calendar
| Week | Dates | Phase | Milestone |
|---|---|---|---|
| 1 | 05-12 – 05-16 | Discovery | Threat model complete |
| 2 | 05-19 – 05-23 | Platform Testing | API & auth coverage |
| 3 | 05-26 – 05-30 | Platform + Wallets | D3: Wallet Flow Model delivered |
| 4 | 06-02 – 06-06 | Smart Contracts (I) | Automated analysis complete |
| 5 | 06-09 – 06-13 | Smart Contracts (II) | D2: SC Audit Report delivered |
| 6 | 06-16 – 06-20 | Reporting | D1 + D4: Final reports delivered |
Week-by-Week Detail
Week 1 — Discovery
- Kickoff call, access provisioning verification
- Architecture documentation review
- STRIDE threat modeling session (2h call)
- Attack surface enumeration, risk register
Week 2 — API & Platform Testing
- Authentication (JWT, OAuth, session)
- Authorization and IDOR
- Input validation and injection
- Rate limiting and abuse prevention
- RNG subsystem initial review
Week 3 — RNG + Wallet Flow
- RNG entropy and seed analysis
- Outcome statistical sampling
- Transaction graph construction
- Cluster analysis and sybil modeling
- Wallet Flow Risk Model (D3) delivered — 2026-05-30
Week 4 — Smart Contracts: Automated Analysis
- Slither + Semgrep automated sweep
- Echidna fuzzing setup and execution
- Manticore symbolic execution
- Result triage, false-positive removal
Week 5 — Smart Contracts: Manual Review + PoC
- Access control + upgrade mechanism review
- Reentrancy + flash loan surface analysis
- Oracle dependency and MEV exposure
- PoC development for Critical/High findings
- Smart Contract Audit Report (D2) delivered — 2026-06-13
Week 6 — Final Reporting
- Platform report: executive and findings sections
- Risk heat map, remediation matrix
- Internal QA review
- Draft submitted for PeraltaCC review
- Platform Security Audit Report (D1) + Remediation Tracker (D4) — 2026-06-20
Milestone Summary
| # | Milestone | Date | Owner |
|---|---|---|---|
| M1 | Engagement kickoff | 2026-05-12 | Both |
| M2 | Access provisioned | 2026-05-12 | PeraltaCC |
| M3 | Threat model complete | 2026-05-16 | VLN |
| M4 | Wallet Flow Model delivered | 2026-05-30 | VLN |
| M5 | SC automated analysis complete | 2026-06-06 | VLN |
| M6 | SC Audit Report delivered | 2026-06-13 | VLN |
| M7 | Platform Audit Report delivered | 2026-06-20 | VLN |
| M8 | Re-test request deadline | 2026-07-06 | PeraltaCC |
| M9 | Re-test report (conditional) | 2026-07-20 | VLN |